3rd stage of construction – soil excavation, anchor input, GWT change

After adding the 3rd stage of construction we follow the previous step and excavate the next layer of soil using again the "Activity" input mode.

3rd stage of construction – soil excavation

Next, we switch to "Anchors" input mode. Pressing the add button then opens the "New anchors" dialog window to enter the required parameters of the pre-stressed anchor (F=185 kN). An anchor cannot be hooked to a vertical interface. Instead, the anchor head must be defined by entering its coordinates – [0.00m, -2.90m].

.

3rd stage of construction – adding anchor

Finally we adjust the ground water table.

3rd stage of construction – adding anchor3rd stage of construction – adding anchor

Performing calculation in the 3rd stage of construction is the last step of overall analysis.