Minimum Dimensioning Pressure
When determining the magnitude and distribution of earth pressures it is very difficult to qualify proportions of individual effects. This situation leads to uncertainty in the determination of earth pressure loading diagram. In reality, we have to use in the design the most adverse distribution in favor of the safety of the structure. For example, in case of braced structures in cohesive soils when using reasonable values of strength parameters of soil along the entire structure we may encounter tensile stresses in the upper part of the structure - see figure. Such tensile stresses, however, cannot be exerted on the sheeting structure (consequence of the separation of soil due to technology of construction, isolation and drainage layer). In favor of the safe design of sheeting structure particularly in subsurface regions, where tensile stresses are developed during computation of the active earth pressure, the program offers the possibility to call the option "Minimum dimensioning pressure" in the analysis.
Minimum dimensioning pressure
The minimum dimensioning pressure is determined using the coefficient k as a fraction of the vertical pressure. For example, k = 0.2 corresponds to a minimum pressure equal to 20% of the vertical pressure.
Its application is selected from the "Minimum dimensioning pressure" drop-down list:
- "Do not consider" – the minimum dimensioning pressure is not applied; only tension cutoff is performed.
- "Consider on earth pressure" – only the earth pressure due to the self-weight of the soil is compared with the minimum dimensioning pressure. The effects of water, surcharge, and other loads are added afterwards.
- "Consider on total pressure including water pressure" – the total pressure, including the effects of water, surcharge, and other loads, is compared with the minimum dimensioning pressure.
If the pressure being compared at a given depth is lower than the minimum dimensioning pressure, it is replaced by the minimum value.
Min. dim. pressure: a - not considered, b – on earth pressure; c – on total pressure
Legend: Brown = original earth pressure, blue = pressure increment due to surcharge, red = minimum dimensioning pressure, green = resulting pressure.